1. Disconnect the evaporative hose (purge solenoid valve side) and install the vacuum gauge..
2. Verify that the intake air hoses are installed securely.
3. Warm up the engine.
4. Measure the intake manifold vacuum while idling (no load) using the vacuum gauge.
If not within the specification, perform the following inspections.
Compression pressure.
Air suction
Installation areas of each vacuum hose
Installation area of throttle body
Installation area of fuel injector
Installation area of PCV valve
Installation area of intake manifold
MZR 2.0: Approx. –68.0 kPa {–510 mmHg, –20.1 inHg}
MZR 2.5: Approx. –70.0 kPa {–525 mmHg, –20.7 inHg}
Non Return Valve Inspection [Skyactiv G 2.0]
WARNING:
Fuel is very flammable liquid. If fuel spills or leaks from the pressurized
fuel system, it will cause serious injury or death and facility breakage. Fuel
can also irritate skin and eyes. To prevent this, always complete the “Fuel
Line Safety Procedure”, while referring to ...
High Mount Brake Light Bulb Removal/Installation
4SD
1. Disconnect the negative battery cable..
2. Remove the trunk lid trim..
3. Remove in the order indicated in the table.
1
Connector
2
Socket
3
High-mount brake light bulb
4. Install in the rev ...
Rear Crossmember Removal/Installation
CAUTION:
Performing the following procedures without first removing the ABS wheel-speed
sensor may possibly cause an open circuit in the wiring harness if it is pulled
by mistake. Before performing the following procedures, disconnect the ABS wheel-speed