CAUTION:
If the wheel and tire sizes are changed, a discrepancy with the speedometer needle whereby it exceeds the allowable range could result in a malfunction. If the wheel and tire sizes are changed, perform the following procedure to change the tire size parameter setting..
1. Connect the M-MDS (IDS) to DLC-2.

2. After the vehicle is identified, select the following items from the initial screen of the M-MDS (IDS).
a. “Module Programming”
3. Select “Programmable Module Installation”.
4. Select menu in the “PCM”.
5. Perform the configuration according to the directions on the screen.
6. Retrieve DTCs by the M-MDS (IDS), then verify that there is no DTC present.
If a DTC(s) is detected, perform the applicable DTC inspection..
Neutral Switch Inspection [Mzr 2.0, Mzr 2.5]
PCM Inspection [Mzr 2.0, Mzr 2.5]Oil Seal (Differential) Replacement [G66 M R]
1. On level ground, jack up the vehicle and support it evenly on safety stands.
2. Remove the aerodynamic under cover No.2..
3. Drain the oil from the transaxle..
4. Remove the front splash shield..
5. Separate the drive shaft and joint shaft from the transaxle..
6. Remove the oil seals u ...
Oil Control Valve (OCV) Removal/Installation [Mzr 2.3 Disi Turbo]
1. Remove the battery cover..
2. Disconnect the negative battery cable..
3. Remove the charge air cooler..
4. Remove the ignition coils..
5. Disconnect the ventilation hose from the cylinder head cover..
6. Remove the cylinder head cover..
7. Remove in the order indicated in the table.
...
Front Door Hinge Removal/Installation
1. Disconnect the negative battery cable..
2. Remove the following parts:
a. Front bumper.
b. Front combination light.
c. Front fender molding.
d. Side step molding.
e. Front fender panel.
f. Front door.
3. Remove in the order indicated in the table.
1
B ...