Joint Shaft Removal/Installation [Skyactiv G 2.0]
Vehicle Speed Sensor (VSS) Inspection [FS5 A EL]Joint Shaft Assembly [Mzr 2.5 (ATX)]
1. Assemble in the order indicated in the table.
1
Bracket
2
Bearing
.
3
Dust seal (RH)
.
4
Dust seal (LH)
.
5
Joint shaft
.
Bearing A ...
Neutral Switch Removal/Installation [A26 M R]
1. Disconnect the negative battery cable.
2. Disconnect the neutral switch connector.
3. Remove the aerodynamic under cover No.2..
4. Remove the neutral switch with the gasket.
5. Install a new gasket and the neutral switch to the transaxle case.
Tightening torque
29—39 N·m {3. ...
PID/Data Monitor Inspection [Two Step Deployment Control System]
1. Connect the M-MDS (IDS) to the DLC-2.
2. After the vehicle is identified, select the following items from the initialization
screen of the IDS.
a. Select “DataLogger”.
b. Select “Modules”.
c. Select “RCM”.
3. Select the applicable PID from the PID table.
4. Verify the PID data a ...