NOTE:
Perform the following inspection only when the transaxle has been overhauled.
1. Perform a road test and inspect the following items:
a. No abnormal noise in each shift position.
b. Smooth shift operation when shifting gears.
c. No gear slipout after shifting gears.
d. Back-up light switch operates correctly.
Information
Inspection After Transaxle Installation [G35 M R]Variable Valve Timing Actuator Inspection [Mzr 2.0, Mzr 2.5]
CAUTION:
Variable valve timing actuator can not be disassembled because it is a precision
unit.
1. Remove the battery cover..
2. Disconnect the negative battery cable..
3. Remove the plug hole plate..
4. Disconnect the wiring harness.
5. Remove the ignition coils..
6. Remo ...
EGR Valve Removal/Installation [Mzr 2.0, Mzr 2.5]
1. Remove the battery cover..
2. Disconnect the negative battery cable..
3. Drain the engine coolant from the radiator..
4. Remove the air cleaner and the air hose as a single unit..
5. Remove the radiator hose (upper, engine side)..
6. Disconnect the EGR valve connector.
7. Remove in th ...
Windshield Wiper Motor Inspection
1. Disconnect the negative battery cable..
2. Remove the following parts:
a. Windshield wiper arm and blade.
b. Front fender molding.
c. Cowl grille.
d. Center cowl grille No.1, No.2
3. Disconnect windshield wiper motor connector.
4. Connect the battery positive voltage to windshield w ...